MUTCD 11th Edition

Traffic control plans that draw themselves

Pick a typical application, enter the posted speed and lane offset, and the taper, cone spacing and advance warning signs lay themselves out to the MUTCD. Change the speed and the whole plan re-computes.

Posted speed limit, off-peak 85th-percentile speed prior to work starting, or anticipated operating speed.

ft

How far traffic is moved sideways — usually the width of the closed lane.

Open this in the plan builder

Merging taper length

245ft

L = W × S² ÷ 60 = 12 × 35² ÷ 60 = 245.0 ft

MUTCD 11th Ed, Tables 6B-3 and 6B-4 — at least L

Plan view

8 devices at 35 ft
245 ft12

Length is to scale; the lateral offset is exaggerated so the taper is legible.

All taper types at these conditions

MUTCD 11th Ed, Table 6B-3

Merging taper

at least L

245 ft

Shifting taper

at least 0.5 L

125 ft

Shoulder taper

at least 0.33 L

85 ft

One-lane, two-way traffic taper

50 ft min, 100 ft max

50 ft

Downstream taper

50 ft min, 100 ft max

50 ft

Channelizing devices

MUTCD 11th Ed, Section 6K.01

Maximum spacing in this taper

1 × 35 mph

35 ft

Devices required

One at each end, evenly spaced between

8

Table 6B-3 states these lengths as minimums. Longer tapers are not automatically better — MUTCD Section 6B.08 notes that extended tapers tend to encourage sluggish operation and delay lane changes, particularly in urban areas with short blocks or frequent driveways.

The plan does the arithmetic

Every number on the sheet traces back to a table in the MUTCD 11th Edition, and every plan prints the citation.

Parametric tapers

Taper length comes from Table 6B-4 and the type multiplier from Table 6B-3. Change the posted speed and the taper re-lays itself.

Correct device spacing

Channelizing devices space at 1× the speed in a taper and 2× on a tangent, per Section 6K.01. The run repopulates as you drag it.

Advance warning series

Signs place at the Table 6B-1 A/B/C distances for your road type, at their MUTCD-minimum sizes.

54 typical applications

Every Chapter 6P figure, from lane closure with flaggers to sidewalk detours, as a starting point.

Per-city conformance

Check the plan against the city’s own published checklist — minimum lane width, pedestrian path, notice period — with the source document cited.

Scaled PDF sheet

Submittal-ready at 1"=20' through 1"=60', on 11×17 or 24×36, with title block, legend and auto-generated sign schedule.

How it works

Four steps from address to submittal

1

Find the site

Search the address and drop the work zone on the aerial.

2

Pick the application

Choose the MUTCD typical application that matches your work.

3

Enter the conditions

Posted speed, lane offset and road type. The geometry computes itself.

4

Export the sheet

Scaled PDF with title block, legend, sign schedule and device takeoff.

Frequently asked questions

What contractors ask before they submit

Stop paying $49 a sheet

Build your first plan free. No credit card, no install.